WaterHistory.org WaterHistory.org
WaterHistory.org Search WaterHistory.org
 
WaterHistory.org WaterHistory.org WaterHistory.org
WaterHistory.org WaterHistory.org
Location Water Use Historic Era Technology Short Bios Multimedia About Home
A History of the Emery County Project

A History of the Emery County Project

William Joe Simonds


Tip

Click Here for a PDF (printer friendly) version

THE EMERY COUNTY PROJECT

Through out the West, irrigation districts have faced many difficulties. One problem that has plagued numerous districts is the lack of significant water storage to capture spring runoff for use during the late irrigation season when natural stream flows are at a minimum. The water users in Emery County, Utah, were faced with such a situation. Construction of small water storage reservoirs eased the situation somewhat, but it was clear that only development of large scale storage could solve the problem. But area water users could not support construction of large scale storage nor could they repay the cost of such development. It was clear that unless some form of outside assistance could be secured, the future of Emery County looked increasingly uncertain. For the water users of Emery County, that assistance came with the passage of the Colorado River Storage Project Act in 1956.

PROJECT LOCATION

The Emery County Project is located in the Green River Basin in east-central Utah. The major towns in the project area are Huntington, Castle Dale, and Orangeville. Joes Valley Dam is located on Seely Creek, a tributary of Cottonwood Creek, about 15 miles northwest of Castle Dale. Water stored in Joes Valley Reservoir is released down Seely Creek to Cottonwood Creek and is diverted from Cottonwood Creek at Swasey Diversion Dam, about 10 miles downstream from Joes Valley Dam. From Swasey Diversion Dam, water flows through existing canals and ditches to serve lands in the Castle Dale area, and through Cottonwood Creek-Huntington Canal for just over 16 miles before it is discharged in the North Ditch. From there, the water flows a short distance to the Huntington North Reservoir, an off-stream storage reservoir formed by the construction of a main dam and two dikes. Water stored in Huntington North Reservoir is released into the Huntington North Service Canal and carried to several canals and ditches for distribution to project lands.

Project lands extend from southwest of Castle Dale northward to the border between Emery and Carbon Counties north of Elmo. Project lands are divided into two sections. The Cottonwood Area consists of lands in the vicinity of Castle Dale and Orangeville, while the Huntington Area is made up of lands around the towns of Huntington, Lawrence, Cleveland, and Elmo. 1

HISTORIC SETTING

Prehistory

The first inhabitants of the Emery County area were nomadic Paleo-Indian hunter-gatherers who entered the area about 12,000 years ago. Although the evidence is sketchy, artifacts discovered suggest that members of the Llano cultural complex inhabited the region about 11,000 years ago. Later inhabitants came from several different phases of the Archaic era.

The most notable pre-historic inhabitants of the Emery Country area were those of the Fremont Culture. Emery County was home to what is known as the San Rafael variant of the Fremont Culture. The Fremont Culture was unique to eastern Utah and western Colorado and began to appear in the region about 1,500 years ago. Most Fremont sites in Emery County date from the Muddy Creek phase from about 1,300 to 1,000 years ago. Fremont dwelling and storage sites have been located throughout the region including in Joes Valley, the canyons of the Wasatch Plateau, and the canyons of the Green River.

The Fremont people were largely sedentary. Evidence indicates the Fremont practiced basic ditch irrigation as well as flood irrigation. Their animal protein came primarily from rabbits, squirrels, deer, and other small game. Artifacts of the Fremont culture which have been found in the Emery County region include a distinctive pottery style known as Emery Gray, and a variety of corner notched projectile points. The most distinctive artifacts of the Fremont Culture in Emery County are elaborate rock art panels which are located throughout the region. Excellent examples of both petroglyph (etched) and pictographs (drawn or painted) rock art panels are found in the area.

Photograph 1. Examining the spectacular petroglyphs of the Rochester Panel, located near Emery County (2000).

The Fremont people disappeared from the Emery County area about 800 years ago. About that time, Shoshonean peoples, ancestors of the Ute and Paiute, moved into the area. It is unknown if the Fremont people were absorbed by the Shoshoneans or if they moved off and joined other peoples, perhaps the Hopi or Pueblo peoples. When the first Anglos entered eastern Utah, the Ute were the primary inhabitants. Although no particular band claimed the Emery County area as their territory, reports of early travelers indicated that the Ute were present throughout the region.2

History

It is unclear when the first non-native peoples entered the Emery County region. The expedition of Juan Maria Antonio Rivera passed near the site of Moab in 1765, but did not trek into the Emery County region. The Dominquez-Escalante expedition also by-passed Emery County in 1776. Two "mountain men," James Workman and William Spencer, became separated from their party on the Arkansas River in 1809. They purport to have wandered through eastern Utah until they met up with a Spanish trading caravan bound for Los Angeles. There are questions about the validity of their story, but if true, they would have been the first Anglos to journey through the Emery County region.

The earliest authenticated account of Anglo penetration into Emery County was Jedediah Smith's expedition of 1826. In the 1830s, Emery County became part of the Spanish Trail, which extended from Santa Fe to Los Angeles. Between 1830 and 1860, numerous expeditions passed through or near Emery County, including expeditions led by Kit Carson (1848), E. F. Beale (1853), John W. Gunnison (1853), and John C. Fréémont (1853-54). In the 1860s, increased Mormon settlement in the Sanpete Valley west of the Wasatch, led to increased exploration of the Wasatch Plateau and likely the Emery County region. In 1865, a conflict between settlers at Manti and the Ute, known as the Black Hawk War, broke out. In mid-1865, two forces of Mormon militia were sent into the Emery County region in pursuit of Ute raiders who had stolen livestock from Mormon settlements in the Sanpete Valley. Although the raiders escaped with their bounty, the militia expedition helped expose the Emery County region to residents of the Sanpete Valley, many of whom would spearhead settlement of Emery County in the following decades. 3

In the mid-1870s, stockmen began moving their herds into the Emery County region. Drawn by the wide-open territory, they sought to relocate their herds away from the crowded ranges to the north and west, and Emery County was the perfect location for them to expand their operations. Many who cared for the herds would become Emery County first permanent Anglo residents.

In late August of 1877, Brigham Young, president of the Church of Later Day Saints (LDS), issued an order to the Sanpete LDS Stake president seeking ". . . at least fifty families [to] locate in Castle Valley this fall." The order led to the founding last Mormon colony settled under the direction of Brigham Young. One week later on August 29, Young, the Great Colonizer, died. During his 30 years as leader of the LDS Church, Young had overseen and directed the establishment of almost 400 towns and villages. The settlement of Emery County was his last.4

Photograph 2.

Montell Seely
Emery County Farmer and Pioneer Enthusiast

Tip

Click here to listen to Montell Seely
See this clip in Quicktime Video Format
(We recommend viewing the movie only if you have a high speed connection - it is 700 Kb)

Soon after issuance of Young's order, several bands of settlers moved out from the Sanpete region headed for Castle Valley (Emery County). They settled along Huntington Creek, Cottonwood Creek, and Ferron Creek. The following spring (1878) several more families moved into the region. In the spring of 1878, Elias Cox and Charles Hollingshead set up a saw mill in Huntington Canyon to provide lumber for the colony. On Ferron Creek, setters plowed lands and began construction of a ditch for irrigation. Most of the early settlers in Castle Valley claimed easily watered bottom lands along the creeks and rivers, and by 1879, most of the best lands had been taken up. Plans were drawn up to construct ditches to carry water to lands further from the streams and rivers. Ditch construction usually took place during the winter, and within a few years, numerous ditches were carrying to lands throughout the region.

Emery County was created by the Utah Territorial Legislature in February 1880 and included what later became Carbon County. The census of 1880 showed 556 people and 84 farms in Emery County, but this figure is likely short as many prominent settlers were inadvertently left off the county roles. By 1890, the population of Emery County had risen to 2,866, and towns had grown from groups of ramshackle cabins to communities with schools, stores, and churches. Early ditches which tended to be small and served limited area were consolidated into large canals serving much greater acreage. Between 1880 and 1900, many significant canals were constructed, including the Huntington Canal (1884), Emery Canal (1885), Cleveland Canal (1885), and the Wakefield Ditch (1880). Many of the early canals are still in service.5

Edward A. Geary, Director
Charles Redd Center for Western Studies
Brigham Young University

Tip

Click here to listen to Edward A. Geary

In the early 1880s, the Denver and Rio Grande Western Railroad began investigating rail routes through the Emery County region. Early plans to locate the railroad through the heart of Emery County were thwarted when the route over the Wasatch Mountains proved to be too steep. The alternative route took the rails through the north-eastern corner of the county, by-passing most of the settlements in the county. While most of the county did not immediately benefit from the railroad, Green River, on the eastern edge of Emery County boomed almost overnight following arrival of the rails.

By 1900, the population of Emery County had reached over 4,600 people. Over 450 farms were operating in the county, growing crops on over 25,00 acres. Irrigation systems were being expanded to bring new lands into production, bringing with them problems which would plague the region for several decades. Water rights conflicts frequently arose, and water theft, known as "midnight irrigation," became common. Most disputes were settled by decree, but a few were contested by violence. During the early 1900s, the residents of Emery County began to experience a problem that was common among irrigators throughout the west: insufficient late season flows. To combat this problem, small storage reservoirs were constructed, providing limited relief. In 1902, a local irrigation convention drafted a petition seeking government assistance under the newly enacted Reclamation Act, beginning a decades-long quest for a federal reclamation project.6

By 1920, the amount of irrigated acreage had increased to over 43,000 acres, but much of the increase was offset by the loss of land through degradation. The underlying soils in Emery County consist of ancient seabeds which contain high levels of salts. Poor drainage and over-irrigation causes the salts to collect on the surface, rendering large areas of land unsuitable for agriculture. The problem first appeared in the 1890s, and in 1903, a Department of Agriculture report stated that over 30% of the developed farmland in Emery County had been abandoned due to degradation. Experimental drainage projects were developed which showed some promise, but the cost proved too high for widespread implementation. To overcome the loss of lands, new lands were brought into production by expanding existing systems and developing new ones.

With expanded irrigation development came expanded settlement has several new towns were established. In addition, the coal industry, which had consisted of a few small mines which provided for local demand, expanded and several large scale operations began. The entry of the United States into World War I created a minor boom in Emery County as agricultural prices rose and manpower shortages caused wages at the mines to rise. Following the war, prices dropped significantly, leading to hard times throughout much of the 1920s. Things improved somewhat during the later years of the decade, but an even more significant collapse came with the onset of the Great Depression in the early 1930s. In addition, severe drought in 1931 and 1934 intensified the economic hardship in the county.

The decade of the 1930s was difficult for the residents of Emery County. The population of the county dropped from over 7,400 in 1920 to a little over 7,000 in 1930, and remained steady through the 1930s. Agricultural prices dropped 40% from their 1929 level, and coal production dropped by half. Water shortages and land degradation continued to be a problems has yet there had been no solution to the long term storage problem. In 1935, only 16,462 acres out of 41,725 acres produced crops. 7

The residents of Emery County benefited from many depression-relief programs, including the Civilian Conservation Corps (CCC). Several CCC camps were established in Emery County. Company 959 established a camp in Joes Valley in May 1933. The camp moved several times in the following years before establishing a permanent camp near Ferron in 1935. A second camp was established at Castle Dale in 1935, and another camp was established at Green River in 1938. During its tenure in Emery County, the CCC built road, bridges and trails as well as building ranger stations and other projects on public lands. Many enrollees settled in Emery County after their discharge from the Corps.8

The drought of the mid-1930 highlighted the need for an augmented water supply. New reservoirs were build and other enlarged. Several small irrigation and ditch companies merged, pooling their resources to provide better service. The desire for a stable water supply renewed interest in Joes Valley as a reservoir site. In 1937, the state planning board approved the idea, and testing at the site was carried out. Local interest promoted the project, seeking federal relief funds for construction. In 1941, the Bureau of Reclamation supported construction of a reservoir in Joes Valley using funding from the Works Progress Administration (WPA) and using CCC labor with local water users paying for about half the project. In order for the project to be feasible, water users from both the Cottonwood Creek and Huntington Creek would have to join together. The Huntington-Cleveland Irrigation District wanted to build a reservoir at Miller Flat, but Reclamation rejected the idea as not feasible and urged the Huntington group to support the Joes Valley plan. Cottonwood Creek water users unanimously supported the Reclamation plan which would have given almost three-quarters of the project's water to the Huntington Creek water users, but the Huntington Creek contingent withheld their support, electing to pursue the Miller Flat Reservoir them selves. Without the support of the Huntington Creek water users, the Joes Valley project was reduced to a low priority project. All projects in the region were put on hold by the outbreak of World War II in 1941.9

Following the end of World War II, service men from Emery County returned home to find relative economic prosperity. County farm income in 1946 was double that of 1940, and the coal mines were operating at fairly high levels. During the post-war years, the county matured and modernized as modern water and sanitation systems were constructed, roads were improved, and many of the luxuries enjoyed by people in less rural areas, like telephones, reached Emery County. While many things in Emery County improved, some things did not. The agricultural sector still suffered from inconsistent water supplies and a lack of significant long term storage. And in the mid-1950s, the region again suffered from a period of low precipitation. It was also during this time that the long sought after reservoir in Joes Valley would become a reality. In 1956, the Bureau of Reclamation receive approval to construct the Colorado River Storage Project which included development of Joes Valley as part of a participating project.10

PROJECT AUTHORIZATION

The Emery County Project was authorized as a participating project of the Colorado River Storage Project by the Colorado River Storage Project Act of April 11, 1956 (Public Law 84-485), a comprehensive program to develop the water resources of the Upper Colorado River Basin. Under the Act, excess revenues from power production at the main Project units, Flaming Gorge, Curecanti, and Glen Canyon, would be used to help repay the construction cost of the participating projects. Water users on the participating projects would only be liable for those project costs allocated to irrigation. Other project costs allocated to flood control and other project functions would be repaid from excess power revenues of the primary project units. 11

Following approval of the Emery County Project, it was necessary for the local water users to form a district to act as the contracting agency for repayment of the project. The formation of this district, a requirement of Reclamation law, highlighted several sectional rivalries which had in the past prevented construction of a reservoir in Joes Valley. In addition, there were concerns over relinquishing water rights to the federal government. But the efforts of the district supporters were boosted by the fact that Emery County was experiencing a drought, and local water users were acutely aware of the need for large scale water storage. The Emery Water Conservancy District was formed on April 4, 1961, and a contract for repayment of almost $3,000,000 of the nearly $8,000,000 project cost was approved by 96% of the voters in May 1962. 12

CONSTRUCTION HISTORY

The first contracts let in association with construction of the Emery County Project were let in late 1962. Those contracts were for construction of a laboratory building, and for construction of streets and a utility system for the Government camp at Castle Dale. The laboratory was completed in August 1962, and the camp in December.

Bids for the construction of Joes Valley Dam were opened on May 2, 1963. The contract was awarded to S.S. Mullen, Inc. of Seattle on May 10. The winning bid was $3,562,260. The contractor acknowledge the notice to proceed on June 21, 1963, setting a completion a date of June 25, 1966. Actual construction began on June 20 with excavations for the access road and preparations for excavation of the diversion tunnel.13

Ground breaking for Joes Valley Dam was held on June 20, 1963. Those in attendance included Utah Governor George Clyde, Utah Senator Frank Moss, Reclamation Commissioner Floyd Dominy, and Reclamation's Chief Engineer Barney Bellport. During the ground breaking ceremony, the dynamite blast which was to commemorate the beginning of construction went off prematurely, prompting a rather frightened outburst from the Commissioner.14

Photograph 3. Ready to set off blast at the Joes Valley Dam groundbreaking ceremony are (from left to right): Senator Frank E. Moss, Commissioner of Reclamation Floyd Dominy, Ray B. Humphrey from Orangeville, and Eugene Johansen, President, Emery Water Conservancy District (1963).

Photograph 4. Startled crowd views blast at the Joes Valley Dam groundbreaking ceremony(1963).

Work on Joes Valley Dam progressed throughout the summer of 1963. Concrete operations began in mid-September with placements in the outlet works conduit. The diversion tunnel, which would be incorporated into the spillway system, was holed through on October 7, and by the end of 1963, foundation excavations were 70% complete while concrete placements in the outlet works was almost 60% complete. Concrete placements in the diversion/spillway tunnel were about 13% complete and the spillway chute was over 60% complete.

Bids for construction of the lower reach of the Cottonwood Creek-Huntington Canal were opened in late November 1963. The contract was awarded to R.A. Heintz Construction Company of Portland, with a winning bid of $1,578,851. Notice to proceed was given on December 21, 1963, although actual construction under the contract began on December 12. 15

Construction activities increased significantly in 1964 with the start of work on the Cottonwood Creek-Huntington Canal and the advancement of work at Joes Valley Dam. The Contract for construction of Swasey Diversion Dam and the upper reach of the Cottonwood Creek-Huntington Canal was let April 30. The contract was awarded to R.A. Heintz which had submitted the winning bid of $645,610. Notice to proceed was given on May 6, with work beginning in mid-July. Clearing for the Swasey Diversion Dam began in July, and the creek was diverted around the construction site at the end of the month.

At Joes Valley, work continued throughout the summer and into the fall of 1964. Clearing of the reservoir area was completed in mid-June. Seely Creek was diverted through the diversion tunnel on August 20, and placement of embankment material began in September. By the end of 1964, embankment operations were advancing steadily, all excavation work was complete, and over 95% of the concrete work was complete. Work on Swasey Diversion Dam and the upper reach of the Cottonwood Creek-Huntington Canal was well advanced, and the lower reach of the canal was more than 2/3 complete.

Photograph 5. Placing concrete in the spillway shaft intake structure at Joes Valley Dam (1964).

The contract for construction of the Huntington North Dam and Dikes was awarded on December 14, 1964. The winning bid of $741,286 was submitted by W. W. Clyde and Company of Springville, Utah. Notice to proceed was issued December 14, with construction activities beginning the same day.16

Construction activity picked up significantly in 1965 with the start of construction of the Huntington North Dam and Dikes in late January. Other activity in association with construction of Huntington North Reservoir included relocation of several ditches which ran through the reservoir area. The ditch relocation was carried out under a separate contract which was let in October 1964. The relocations were completed in mid-June 1965.

In late April, work on the Swasey Diversion Dam was sufficiently complete to allow diversion of Cottonwood Creek over the overflow section of the dam. The last major contract to be let in association with construction of the Emery County Project was let in late June. The contract for construction of the Huntington North Service Canal and Huntington North Feeder Canal, was awarded to E.V. Chettle in late June. The accepted bid was $274,566. The contractor received the order to proceed in early August.

On May 17, workers for S.S. Mullen began placement of zone 1 materials at Joes Valley Dam. The embankment was competed on October 22, and on November 3, the diversion tunnel was blocked, allowing storage to begin in Joes Valley Reservoir. By the end of 1965, Joes Valley Dam was essentially complete with only placement and grouting of the diversion tunnel plug and minor concrete work remaining. The contracts for construction of Swasey Diversion Dam and both reaches of the Cottonwood Creek-Huntington Canal were accepted as complete on December 17.17

Photograph 6. Start of the embankment construction on Joes Valley Dam (1965).

Photograph 7. Work progressing on the earthfill at Joes Valley Dam (1965).

All major features of the Emery County Project were completed during the first half of 1966. Huntington North Dam and Dikes were completed on January 6, and filling of the reservoir began in April. Construction of the Huntington North Feeder Canal was accepted as complete on April 8, and the Huntington North Service Canal on July 23. Joes Valley Dam was accepted by Reclamation on June 23, and deliveries of project water began on July 1, with deliveries to fields in the Cottonwood Area. 18

Joes Valley Dam is a zoned earthfill dam, 192 feet high, 750 feet long, and containing 1,290,000 cubic yards (cy) of material. Joes Valley Reservoir a maximum of 62,460 acre-feet (af) and as a surface area of 1,170 acres at capacity. Swasey Diversion Dam, ten miles downstream from Joes Valley Dam, is a concrete overflow weir with earth embankment wings. It is 11 feet high and 75 feet long and has a diversion capacity of 165 cubic feet per second (cfs). Swasey Diversion Dam diverts project water into the Cottonwood Creek-Huntington Canal which extends northward for just over 16 miles, ending at the historic North Ditch. The Cottonwood Creek-Huntington Canal is concrete lined with an initial capacity of 165 cfs.

The Huntington North Feeder Canal heads at North Ditch and runs southward about 1/2 mile to the Huntington North Reservoir. It is concrete lined and has a capacity of 100 cfs.

Huntington North Dam and Dikes are of zoned earthfill construction and form the Huntington North Reservoir. The main dam is 74 feet high and 2,897 feet long. The East Dike is 31 feet high and 1,185 feet long, and the West Dike is 24 feet high and 1,919 feet long. The total volume of the main dam and two dikes is 967,000 cy. Huntington North Reservoir has a maximum capacity of 5,420 af and a surface area of 242 acres. The Huntington North Service Canal heads at the East Dike of the Huntington North Reservoir and goes generally eastward for about 3 and a half miles, ending at the historic Cleveland Canal. It is concrete lined and has a capacity of 35 cfs.19

POST CONSTRUCTION HISTORY

The Emery County Project was transferred from construction status to operational status on January 1, 1967. In 1968, just over 16,500 acres of project land received water. The amount of irrigated acreage reach 17,200 acres in 1970, the same year the Emery Water Conservancy District assumed operation and maintenance of the project irrigation facilities. In early 1969, the United State Government and the Utah Division of Parks and Recreation signed an agreement whereby the State of Utah would develop and administer recreation at the Huntington South Reservoir.

Construction of a project drainage system began in November 1971, with work on the open pilot drain. This work was completed in July 1972. Construction of the first block of drains began in May 1973, and was completed in November. Contracts for construction of additional drains were let in 1974 and 1976.20

In the late-1960s and early-1970s, Emery County underwent significant economic change. Coal production in Emery County and the surrounding area had reached a peak in the late-1950s, declining steadily throughout the 1960s. In February 1969, Utah Power & Light announced plans to construct two large coal-fired powerplants in the area. The Emery County area was a logical place to locate the plants. With the coal mines nearby, the costs of transporting fuel to the plants would be significantly reduced. But there was also a need for large amounts of water. In all, the powerplants would require 27,000 af of water for their operations. Utah Power & Light was able to acquire 15,000 af of primary water right on Huntington Creek, and an additional 6,000 af from Cottonwood Creek. To obtain the remaining 6,000 af, Utah Power & Light turned to the Cottonwood Creek Consolidated Irrigation Company, seeking a share of its project water stored in Joes Valley Reservoir. While there was some concern about the effects of large scale development on Emery County, most recognized the enormous economic benefits that would be realized by such development. Many farmers agreed to sell a portion of the their water while others tendered all of their water stock, effectively abandoning their farming operations to help secure the counties economic future. By February 1970, sufficient water had been secured to enable Utah Power & Light to proceed with construction of the first generating units. 21

Construction of the Utah Power & Light generating plants had an immediate impact on Emery County. Population in the county grew from just over 5,000 in 1970, to a peak of over 13,000 in 1983. In addition, Emery County went from being one of the poorest counties in Utah to being one of the richest. The first powerplant, the Huntington Powerplant, located eight miles west of Huntington, began operating its first unit in 1974. The second unit came on-line in 1977. The second powerplant, the Hunter Powerplant, located three miles south of Castle Dale, began operations in 1978, when the first of its three units went on-line. The second unit entered service in 1980, and the third in 1983. Today, the two powerplants employ over 500 people. In addition, the mines which provide high quality , low sulfur coal to the powerplants employ over 600 people. The development of the power industry in Emery County and the subsequent revitalization of the coal industry has provided the county with the economic stability it had long sought.22

In 1974, the Congress passed the Colorado River Basin Salinity Control Act which authorized the construction and operation of facilities in the Colorado River Basin to help control the salinity level of water delivered to Mexico as required under Minute 242 of the International Boundary and Water Commission. Title II of the Act provided for the specific construction of several salinity control units in Colorado, Utah, Arizona, and New Mexico. One of those units was the Price-San Rafael Unit in Emery and Carbon Counties. Almost 430,000 tons of salts are contributed to the Colorado River system from the Price and San Rafael River Basins each year. Of that amount, almost 60% is attributed to agriculture in the form of irrigation run-off and canal seepage. To combat this problem, Reclamation proposed several solutions including improvements to irrigation systems, capturing agricultural drainage for other uses, disposing of saline water by deep-well injection or in evaporation ponds, and retiring land from irrigation. Of the proposed solutions, improving irrigation systems proved to be the most viable based on effectiveness and acceptability.

Photograph 8. Aerial view of the Huntington Powerplant, one of 2 powerplants in Emery County that get water from the project (1998).

In the mid-1990s, Reclamation began a program of converting historic, un-lined canals to buried pipe to reduce or eliminate losses due to seepage. This program did not involve piping any canals constructed under the Emery County Project, which are all concrete-lined, but rather canals built during the early decades of settlement. Because of the historic nature of those canals, Reclamation, in cooperation with State and local organizations, is developing a program to interpret the historic significance of those early canals so that present and future generation will know about the important role those canals and their builders played in the settlement of Emery County.23

SETTLEMENT OF PROJECT LANDS

The authorized purpose of the Emery County Project was to supply supplemental water to over 18,000 acres of mostly previously developed farm and pasture land. As such, there were no new lands withdrawn for settlement under the project. The addition of a reliable supply of water for irrigation stabilized the agricultural economy of the region. In the 1970s, the acreage available for service was reduced by 4,600 acres as 6,000 af of project water was reallocated to help support development of the power industry. The development of the power industry was a catalyst for growth and development in Emery County, providing hundreds of construction and support jobs. Following construction of the power facilities, the economic boost continued as the coal industry stepped up production to provide fuel for the powerplants. Through the reallocation of a portion of the project's water from agriculture to power generation, the project provided indirect support for the economic and population growth in the region.

In 1995, the population of Emery County was just over 10,400, down slightly from 11,400 in 1980 when construction of the area's power facilities was at its peak.24

PROJECT BENEFITS AND USES OF PROJECT WATER

The primary benefit of the Emery County Project is irrigation. The project provides supplemental water to about 250 full and part-time farms covering more than 18,000 acres. In 1992, the most recent reporting year, over 15,700 acre of land received project water. The primary crops grown consist of forage crops such as alfalfa hay and irrigated pasture. The total project crop value for 1992 was just over $2,200,000.

Photograph 9. The Emery County Project provides irrigation water to approximately 250 farms covering 18,000 acres (1998).

The project also supplies 6,000 acre-feet (af) of water for electric power generation at three powerplants owned and operated by Utah Power & Light. The availability of project water for power generating purposes was critical to Utah Power & Light's decision to build its powerplants in the area. The jobs created by the power industry have been a significant boost to the area's economy. In addition, dozens of jobs were created at area coal mines that supply coal to the powerplants, further extending the benefits of the project.

Recreation is also an important benefit provided by the project. Recreation areas at Joes Valley Reservoir and Huntington North Reservoir annually host more than 200,000 visitors each year. Boating, fishing , and camping are the most popular activities enjoyed at these areas. Recreation at Joes Valley Reservoir is administered by the United States Forest Service, while activities at Huntington North Reservoir are administered by the Utah Division of Parks and Recreation. 25

CONCLUSION

The people of Emery County have always faced challenges: build communities in the arid and inhospitable wilderness, provide for the needs of those communities, and find ways for the communities to grow and prosper. The development of the Emery County Project helped the people of the region to overcome many challenges and provide a solid base on which the region could grow. As Emery County moves into the new century, the Emery County Project will continue to contribute to the solid base from which the people of the county can rise to meet the challenges which confront them.

ABOUT THE AUTHOR

William Joe Simonds was born and raised in Colorado and has a clear understanding of the importance of water in the American West and its influence on the development of that region. He attended Colorado State University where he received a BA in History in 1992 and a Masters in Public History in 1995. He lives with his wife and two children in Fort Collins, Colorado.

Notes

BIBLIOGRAPHY

Archival Materials

National Archives and Records Administration, Rocky Mountain Region. Record Group 115. Records of the Bureau of Reclamation. Project Histories, "Emery County Project," Vol. I - XV, 1962 - 1976.

Government Documents and Publications

Department of the Interior, Bureau of Reclamation. Summary Statistics, Water, Land, and Related Data, Denver: US Government Printing Office, [1995].

Department of the Interior, Bureau of Reclamation. Repayment of Reclamation Projects.

Washington: U.S. Government Printing Office, 1972.

Department of the Interior, Water and Power Resources Service. Project Data. Denver: US Government Printing Office, 1981.

Books

Geary, Edward A. A History of Emery County. Utah Centennial County History Series. Salt Lake City: Utah State Historical Society, 1996.

Sturtevant, William C., ed. Handbook of North American Indians. Vol. 11, Great Basin.

Washington DC: Smithsonian Institution, 1986.

Electronic Resources

"Colorado River Basin Salinity Control Program - Overview," Project Dataweb, Bureau of Reclamation. http://dataweb.usbr.gov/html/crwq.html. September 5, 2000.

"CRBSCP - Price-San Rafael Rivers Unit, Utah," Project Dataweb, Bureau of Reclamation. http://dataweb.usbr.gov/html/price-san.html. September 5, 2000.

"Emery County Project Engineering Data," Project Dataweb, Bureau of Reclamation, http://dataweb.usbr.gov/html/ucemeengdata.html. June 26, 2000.

"Emery Water Conservancy District, Emery Unit General Description," http://www.ewcd.org/history/sys_desc/. March 2, 2000.

"USA Counties - Emery County, Utah, Summary Report" http://govinfo.library.orst.edu/cgi-bin/usaco-list?30-015.utc. July 21, 2000.

"Utah Power." http://www.utahpower.net. June 1, 2000.

Oral History Interviews

Johansen, Oral Eugene, Clyde Conover, and Mack Bunderson, Interview by Wm. Joe Simonds, 13 April 2000, transcript, Bureau of Reclamation Oral History Program, Denver, Colorado.

Journals and Magazines

"Major Recent Contract Awards." Reclamation Era, February 1964, 24.

"Major Recent Contract Awards," Reclamation Era, February 1965, 32.

"Major Recent Contract Awards," Reclamation Era, November 1965, 116.

FOOTNOTES

1. Department of the Interior, Water and Power Resources Service, Project Data, (Denver: US Government Printing Office, 1981), 453-455; "Emery Water Conservancy District, Emery Unit General Description," http://www.ewcd.org/sys_desc/, March 2, 2000.

2. William C. Sturtevant, ed. Handbook of North American Indians (Washington DC: Smithsonian Institution, 1986), vol. 11, Great Basin, 163-172; Edward A. Geary, A History of Emery County, Utah Centennial County History Series, (Salt Lake City: Utah State Historical Society, 1996), 17-22.

3. A History of Emery County, 24-40.

4. Ibid., 47-59.

5. Ibid., 62-107.

6. Ibid., 107-174, 184-186.

7. Ibid., 260, 274-275, 277-278.

8. Ibid., 282-284.

9. Ibid., 297-299.

10. Ibid., 315, 317-345, 348-351.

11. Department of the Interior, Bureau of Reclamation, Repayment of Reclamation Projects, (Washington: U.S. Government Printing Office, 1972), 109.

12. A History of Emery County, 348-349.

13. National Archives and Records Administration, Rocky Mountain Region, Record Group 115, Records of the Bureau of Reclamation. Project Histories, "Emery County Project," Vol. I, 1962, 7; Vol. II, 1963, 4.(hereafter cited as Project Histories, "Emery County Project," followed by volume number, year, and page number(s).)

14. Oral Eugene Johansen, Clyde Conover, and Mack Bunderson, Interview by Wm. Joe Simonds, 13 April 2000, transcript, Bureau of Reclamation Oral History Program, Denver, Colorado (hereafter cited as "Johansen, et al"); Project Histories "Emery County Project," Vol. II, 1963, 1.

15. Project Histories "Emery County Project,"Vol. II, 1963, 4-5; "Major Recent Contract Awards," Reclamation Era, February 1964, 24.

16. Project Histories "Emery County Project," Vol. III, 1964, 4-5, 38, 40-41, 43, 51; "Major Recent Contract Awards," Reclamation Era, February 1965, 32.

17. Project Histories "Emery County Project," Vol. IV, 1965, 5-8, 29, 38, 41, 48, 62, 67, 71-71; "Major Recent Contract Awards," Reclamation Era, November 1964, 116.

18. Project Histories, Emery County Project, Vol. V, 1966, 1, 3-5.

19. Project Data, 456, 459; "Emery County Project Engineering Data," Project Dataweb, Bureau of Reclamation, http://dataweb.usbr.gov/html/ucemeengdata.html, June 26, 2000.

20. Project Data, 455; Project Histories "Emery County Project," Vol. XV, 1976, 56-58.

21. A History of Emery County, 327-329, 359-360.

22. Ibid., 366-372; "Utah Power," http://www.utahpower.net, June 1, 2000.

23. A History of Emery County, 416-417; "Colorado River Basin Salinity Control Program - Overview," Project Dataweb, Bureau of Reclamation,http://dataweb.usbr.gov/html/crwq.html, September 5, 2000; "CRBSCP - Price-San Rafael Rivers Unit, Utah," Project Dataweb, Bureau of Reclamation,http://dataweb.usbr.gov/html/price-san.html, September 5, 2000.

24. "USA Counties - Emery County, Utah, Summary Report" http://govinfo.library.orst.edu/cgi-bin/usaco-list?30-015.utc. July 21, 2000; Project Data, 453, 455.

25. "Utah Power,"; Johansen, et al; Department of the Interior, Bureau of Reclamation, Summary Statistics, Water, Land, and Related Data, (Denver: US Government Printing Office, [1995]).

   Quick Links
 » Travel Info
 » Teaching Aids 
Programming and Design by Moki Systems, a Utah Ruby on Rails consultancy with content provided by USBR Provo Area Office.
Accu-tech Auto Wisp-router.com